G.Cibinetto.
Transcript
G.Cibinetto.
Babar: stato dell’esperimento Gianluigi Cibinetto INFN - Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Outline • Stato generale: – – – – • Stato dei rivelatori – – • Run4 PEP II Detector upgrade Analisi SVT IFR Stato del progetto LST Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 RUN 4 PEP-II Delivered Luminosity in RUN 4 The Seeman scenario Gianluigi Cibinetto – INFN Ferrara PEP-II Delivered Luminosity since 1999 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Daily recorded luminosity Trickle M D R O D Gianluigi Cibinetto – INFN Ferrara holidays R O D c h ill e r Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Run 4 Progress: Trickle Injection • Keeps LER at constant current by continuously injecting positrons at 1-10Hz. PEP has learned to ameliorate the associated backgrounds. • The injected bunch causes backgrounds in BaBar. An L1 trigger inhibit window around injection is used to control deadtime. • Top-off of HER is every 60-90 mins instead of 45mins. Machine stability is improved. • Demonstrated gain in integral luminosity of >15% compared to normal mode of operation. • Injection time markers allow analyses to filter injection background contamination. The loss to this filtering appears to be small compared to the gain in integrated luminosity. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Run 4 Progress: Trickle Injection Best shift, no trickle Best shift, trickle Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 BaBar Data Taking Records PEPII peak Luminosity (1/24/04) 7.31x1033 cm-2 sec-1 in a shift (Owl 1/26/04) 176.5 pb-1 in 24 hours (1/26/04) 513.4 pb-1 in 7 days (1/20/04 - 1/26/04) 2.88 fb-1 in a month (January 2004) 7.39 fb-1 in 30 days (11/23/03-12/22/03) 9.38 fb-1 Data sample collected 160.20 fb-1 1999 1.62 2000 23.76 2001 40.05 2002 31.32 2003 56.71 2004 6.74 Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 La sfida con Belle Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Fall –Winter 2003-2004 PEP II Improvements • Number of bunches: – June 2003: 1030 bunches in the by-3 pattern. – November 2003: 1230 bunches in the by-2. – January 2004: 1317 bunches in the by-2. • HER and LER RF stations added to beam. – I- to 1376 mA peak. – I+ to 2430 mA peak. • Trickle charging – All data now taken in trickle charge mode (LER only). Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Summer-Fall 2004 PEP-II Improvements • • • • • • • • • • IR2 south forward shield wall Add LER RF station Add HER RF station Two new “Frascati” longitudinal kickers New electrodes for transverse kickers Add fans to all HER bellows IR2 new vacuum chambers (Q5 and Q2?) Alignment work (quadrupole rolls) New LER synchrotron light monitor New pulsers for injection magnets PEP II GOALS Seeman scenario Gianluigi Cibinetto – INFN Ferrara Date Total recorded (fb-1) July 2003 132 July 2004 230 July 2006 518 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Detector Upgrade • SVT – Proceed with planning for module replacement in 2005 – Proceed with engineering to allow for future SVT rotation • IFR – Barrel replacement – IR2 south forward shield wall Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 About the 2003 physics harvest • 2003 has been a fruitful year for Physics results in BABAR • The harvest contains the very exciting discovery by BABAR of DsJ (2317) which triggered the discovery of other 2 charm states first seen by BELLE, one DsJ (2460) and the other a Charmonium state X (3870). • First measurement by BABAR of π0 π0 Branching Fraction • Preliminary results from Babar and Belle on b→s penguin (in particular φ Ks decay channel) Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Risultati previsti per Moriond • Update of the measurement of Vub with two different technique: – Measurement of the Inclusive Electron Spectrum in Charmless Semileptonic B Decays Near the Kinematic Endpoint – from semileptonic B decays using the lepton energy and q2 • Search for the decay B0 Æ ρ0ρ0 and constraints on α using an isospin analysis • Measurement of sin(2β+γ) from B Æ Dρ • Update of CP Asymmetries and the CP Content of the Decay B0 Æ D*+D*- • Update of sin(2β) measurement • Update of Time dependent CP violation in B Æ ππ Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Publications: BABAR vs. Belle BABAR Belle <2003 34 54 2003 43 25 Total 77 79 • • • 250 2003 was an outstanding year for BABAR papers! 4 more papers have made it through final, collaboration-wide review and are almost ready to submit. By year of submission. (2003 includes submitted papers.) Integ. luminosity/run Cumulative luminosity 200 • Run 4 is on track to deliver 100 fb-1. 150 • • This will effectively double the amount of data for most analyses. For summer 2004, the goal is to update all major analyses with a large fraction of Run 4 data. 100 50 0 Gianluigi Cibinetto – INFN Ferrara Run 1 Run 2 Run 3 Run 4 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Stato dell’SVT • Dose budget • Radiation damage study – at Elettra – at SLAC and LBL • Unexpected Radiation Effect • SVT rotation • LTTF conclusions Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Dose Budget RUN3+RUN4 dose is 40-60% of RUN1+RUN2. Consistent with delivered luminosity (+55%). Accumulated dose is within the budget but still an important issue. Radiation effects are visible on the chips most exposed to radiation, however it is a confined problem. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Sensors irradiated to 9 Mrad - and they keep on working! • Radiation damage study carried out by Calderini, Bettarini, Bondioli, Marchiori, Rizzo, Bosisio, Dittongo at Elettra facility in Trieste with 0.9 GeV e- beam • Irradiated half-module well past type inversion in 1-2 Mrad steps • Measured charge collection efficiency with automated laser scan • Small (6-8%) loss of CCE, otherwise sensors fully functional • Plan follow-on study of AToM chip irradiation Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Damage to the Atom chips Increase in noise Decrease in gain Digital failures All these issues have been addressed in the past with projects of measurements aimed to quantify the impact on the SVT operation and lifetime AToM chip threshold offset Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Irradiation tests on the Atom chips Gain decrease ~ 3%/Mrad Noise increase ~ 16%/Mrad (α term) Noise increase ~ 19%/Mrad (β term) Gianluigi Cibinetto – INFN Ferrara Radiation tests performed on Atom chips in 2001 using Co60 sources at SLAC and LBL Chips powered and running during irradiation noise=α+β Cload Foreseen decrease of signal/noise down to a factor 2 (mid plane). This determines an upper limit on the ATOM chips lifetime (5Mrads). No digital failure observed up to 5 MRads Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Merging together the information from sensors and front end electronics S/N Total AToM Ileak Using a figure of merit of S/N > 10, a reasonable budget is set at 5 Mrads Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 • Unexpected Radiation Effect SVT BW Midplane Module Roma 2-3 febbraio 2004 Radiation effects are visible on the FEE: 2 chips per ROS. AToM chip Threshold DAC Offset. Threshold offset averaged over each chip Behavior seen in 8 AToM chips so far: L1, FW phi & z (4) L1, BW z (2) L2, FW z (2) Threshold per channel ~1.1 MRad Behavior not seen on east (LER) side despite similar doses Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Efficiency of West side Midplane Module for Hit on Track Small drop in efficiency once threshold is raised to reduce occupancy to normal level (15% efficiency loss for 2/7 chips => 5% loss averaged over module) However it is a confined problem: 2/7 chips per Read Out Section on 4/208 ROS are affected Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 New Idea: Rotate the SVT • Distribute midplane dose onto several regions/modules to extend SVT life • Requires removal of support tube and uncabling, but not removal of the SVT • An engineering concept for the rotation was developed by F. Goozen & R. Kerth • Needs ~2 months engineering time to complete design • Small impact on module replacement schedule Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 LTTF Major Conclusions & Recommendations • Proceed with planning for module replacement in 2005 • Proceed with engineering to allow for future SVT rotation • Module replacement could probably be delayed beyond 2005 if desirable for other reasons – – – • assuming AToM threshold shift does not spread need more studies to understand the effect re-assess in ~6 months Delay of SVTRAD pin diode replacement would compromise radiation monitoring & protection; develop a contingency plan Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Stati dell’IFR • Efficienza del rivelatore • Modifiche al software • Trickle injection • Studio del background Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Forward endcap efficiency • The efficiency is evaluated from collisions runs using muon pairs – We observe an efficiency loss in the most external layers (12, 13, 14) when the backgrounds are high. • The overall efficiency of the first 12 layers in the forward endcap, evaluated on cosmics runs is constant between run 3 and run 4 The forward endcap has been completely replaced in summer 2002 Collision: Efficiency loss per month: 0.99% Cosmics: Efficiency loss per month: 0.04% Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Runs 3-4 efficiency Barrel - Backward endcap Average efficiency Average efficiency of chambers with efficiency > 10 % Percentage of chambers with efficiency < 10 % Gianluigi Cibinetto – INFN Ferrara Efficiency gain due to the HV raise (~ +4%) This stress a lot the chambers. Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Software changes • • • CM2 converted data uses new Kalman swimmer Track fit χ2 provides better separation between π & µ A test selector shows significant improvement for low p and small ϑ in a small sample of Run 3 CM2 data Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Trickle injection Sum of forward east layers 13 & 14 currents (µA) vs. Run number September October November December December November • Currents – Usually lower than during normal operations • IFR Safety – No HV trips in the forward endcap Gianluigi Cibinetto – INFN Ferrara October Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Forward endcap backgrounds • Backgrounds in the outermost layers are a concern for the IFR – Backgrounds are too high to leave layers 15 and 16 HV on – During the worst background conditions, layer 14 has frequent trips 5 10 6 4 10 6 3 10 6 2 10 6 1 10 6 Layer 15 off during normal data taking Gianluigi Cibinetto – INFN Ferrara Layer 1 Layer 2 Layer 3 Layer 4 Layer 5 Layer 6 Layer 7 Layer 8 Layer 9 Layer 10 Layer 11 Layer 12 0 Layer 14 – Make the primary source of the problem more visible at MCC • An EPICS display that shows predicted noise rates is under development • This will allow PEP tuning the beams without our HV on • Fast scalars monitoring already available at MCC – Shielding Layer 15 • Measures taken Inner layer rates due to luminosity and HER Outer layer rates follow LER beam losses Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Shielding test Run 40832 Layer 15 Layer 15 Layer 14 • A steel block (36” × 18” × 8”) was put up during the October ROD at the face of the forward endcap – Backgrounds are reduced by a factor > 10 Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Forward endcap shielding Shielding wall • • • • Parts and tooling have already been made Part of the installation has been done during the Xmas shutdown Complete installation needs one more week of downtime Finish in summer Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Stato del progetto LST • Milestones • Produzione e controllo della qualita’ • Primi moduli assemblati a Princeton • Test Tube • Elettronica • Software Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 LST Milestones successfully passed • • • • • • • • • • • • • • • Dec 15 ’02 June 12 ‘03 June 15 June 22 June 27 June 30 July 17 Aug 1 Aug 26 Aug 27 Sept 3 Oct 1 Oct 22 Nov 10 Nov 30 ---------------- • • • • • Dec 15 Dec 18 Jan 7 ’04 Jan 9 Jan 14 ------ Gianluigi Cibinetto – INFN Ferrara BaBar chooses LST for IFR Upgrade EPAC Review Approves LST Proposal Cost/Schedule/WBS prepared INFN Gruppo Uno Evaluation BaBar IFC Approves Project Large/Small Cell Decision Electronics Design Review Place Orders for Tubes & Small parts Q/A Review Install Test Module in BaBar Fire safety approval for materials (tubes, strips, cables) Decide to read out Phi via wire signals instead of strips Mechanical, Schedule (Installation) & Budget Review Tube Production begins! Orders placed for components: electronics, crates, HV system, signal cables, HV cables Phi Readout plane & Z-strip production begins at SLAC First shipment (~5%) of tubes to Princeton/OSU Q/C systems operational at OSU, Princeton First module assembled at Princeton First module passes Q/C tests Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 LST Remaining Milestones • • • • • • • • • • • • • • • • • • Feb 9 --Mar 1 ---Mar 15 -Apr 2 --Apr 10 -Apr 15 --May 1 -Apr 30 -May 20 -May 25 -May 27 -Jul 31 -Aug 1 -Aug 15 -Oct 8 -Oct 15 -Jul 2005 -- Gianluigi Cibinetto – INFN Ferrara First module assembled at OSU 168 “standard” tubes shipped to Princeton 168 tubes (partially 7-cell and layer 18) shipped to Princeton Crates complete, Electronics tests begin 2% of modules shipped to SLAC Q/C system operational at SLAC 320 Tubes shipped to Princeton Installation tooling complete Electronics complete Gas system assembled, under test at SLAC Electronics, crates, HV shipped to SLAC Installation Readiness Review 336 tubes shipped to Princeton Ship all modules for 2 sextants to SLAC Final 334 Tubes shipped to Princeton Q/C begins at SLAC LST module construction complete (6 sextants+spares) RPC removal begins Installation of 2 sextants begins Installation of 2 sextants complete Run 5 begins Install remaining 4 sextants Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 La Pol. Hi. Tech. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Qualita’ della superficie grafite • La qualita’ della grafite e’ uno dei parametri che influisce maggiormente sul funzionamento delle camere. • L’uniformita’ dello strato di grafite viene ispezionato visivamente dagli operatori della Pol. Hi. Tech. • Ogni difetto viene catalogato: – – – – • Rough surface Unpainted spot Small point Well Repaired Unpainted spot e Small point vengono riparati a mano dall’operatore. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Misure della resistivita’ Misure di resistivita’ sia sul fondo che sulle alette. La misura sul fondo viene effettuata automaticamente da una macchina La misura sulle alette e’ fatta da operatori della PHT I dati vengono analizzati dal personale INFN e discussi con i responsabili della PHT. Circa il 10% delle camere e’ stato trovato fuori specifica. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Conditioning Il conditioning e’ di fondamentale importanza per il buon funzionamento delle camere. Viene effettuato su ogni tubo un ciclo di HV training di una settimana in cui la camera viene portata fino ad una tensione di 5900V in massimo 3 giorni e poi tenuta a 5700V fino alla fine della settimana. Tutti i tubi che hanno correnti superiori a 400nA vengono scartati. Gianluigi Cibinetto – INFN Ferrara V VS. T Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Misura del plateau Plateau Measurement, First Seven LST's 3500 3000 Counting Rate, Hz 2500 Tube 11 Tube 9 2000 E’ richiesto che ogni camera abbia un plateau in singola di almeno ~400V Tube 1 Tube 13 Tube 21 1500 Tube 5 Tube 12 1000 500 0 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400 5500 High Voltage, Volts Gianluigi Cibinetto – INFN Ferrara LST_36 VS. VOLT 5600 5700 5800 5900 6000 6100 Alcuni esempi di plateau in singola dei primi tubi prodotti alla Pol Hi Tech Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Source Scan exposes Pinnacle Pinnacle #1 The calibration grid space is 0.35mm. The big pinnacle long dimension is ~0.35mm. At 5700V, open the shutter, initial current is 1.5µA, after 5 seconds, it jumps to 2.4µA, which indicates self-sustaining discharge mode. Even close the shutter, the current is still at 1.5µA. One has to turn off the HV to stop it. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Scan con la sorgente In letteratura si trova una stretta corrispondenza tra tubi che falliscono il test con la sorgente e tubi che falliscono il test di lungo termine. cur:step 1600 1400 1200 1000 800 Lo scan con la sorgente in piu’ fornisce una radiografia della camera e permette un feedback immediato, importante per la produzione. 600 400 200 0 0 20 40 60 80 100 120 Il piano iniziale prevedeva test di lunga durata a PHT e con sorgente in USA. Per le prime spedizioni abbiamo scambiato l’ ordine dei test. cur:step 1800 1600 1400 1200 1000 800 Per quelle successive entrambi i test verranno fatti alla PHT, dove è pronto il setup per testare fino a 450 tubi. 600 400 200 0 0 20 40 60 80 100 120 cur:step 1400 1200 1000 800 600 400 200 0 0 20 40 60 80 100 cur:step 1200 1000 800 600 400 200 0 0 20 40 Gianluigi Cibinetto – INFN Ferrara 60 80 100 120 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Long term test • Alle camere e’ richiesto di passare un periodo di perfetto funzionamento di 30 giorni alla tensione di 5700V. • Vengono scartate tutte le camere che tirano oltre 200 nA per piu’ del 5% della durata del test • Il test di lungo termine e’ totalmente gestito dall’INFN. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Shift organization at PHT At PHT during production there will be 3 shifters + 1 production manager: Shifter duties: source scan test long term test capacitance measurement overseeing of other important measurements maintenance of the QC machinary The granularity of the shifts is 1 week Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Stato della produzione (I) • La fase di commissioning e’ durata fino alla fine di novembre – Tuning delle macchine da parte della Pol. Hi. Tech. – Installazione infrastrutture QC • La produzione delle camere e’ a regime dalla meta’ di Dicembre. – Rate di tubi assemblati: 15 tubi al giorno • Ritardi e interruzioni della produzione per: – Difetti della grafitatura evidenziati sia dall’ispezione visiva, sia dal conditioning (inizio della produzione) – Inagibilita’ della fabbrica dovuto alla rottura del sistema di riscaldamento – Sospensione del conditioning per rottura di un flussimetro di massa – Accorciamento copertura tubi ( circa 130) a causa di lunghezza fuori specifica di 2 cm Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Stato della produzione (II) • A oggi (30-01-04) sono stati costruiti piu’ di 300 tubi, di questi: – 24 sono a Princeton dalla fine di Dicembre e funzionano molto bene – 50 hanno passato conditioning, plateau e scan con sorgente e saranno spediti negli USA il 9 Febbraio. – 132 sono attualmente sotto conditioning – 100 sono assemblati e in attesa di essere condizionati • Il sistema di Quality Control e’ funzionante e ben integrato con l’attivita’ di produzione. – Il sistema di test e’ in grado di assorbire la quantita’ di tubi prodotta giornalmente dalla ditta – Il lavoro del personale INFN e’ fondamentale per la diagnostica e la certificazione della qualita’ delle camere – Il sistema di QC e’ in grado di segnalare con adeguata tempestivita’ difetti sistematici o casuali delle camere prodotte. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 First 24 tubes arrive Jan 2 in Princeton All tubes survived the trip Test stand in operation in Hi-Bay area Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Performance of first 24 tubes – HV plateaus • More conditioning increases plateau widths • All 24 tubes are “fine” Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Gianluigi Cibinetto – INFN Ferrara First production module assembled Jan 9 Roma 2-3 febbraio 2004 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Performance of first module: ~ 800 volt HV-Plateau!!! “Naked” tubes Before assembly. ~1 day conditioning Assembled in module. ~1 further day of conditioning Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Structure of the test module Top strip plane (bottom plane not seen) Forward end extension box Anode wire readout LEMO adaptor Gianluigi Cibinetto – INFN Ferrara Aluminum box Trigger counter OSU baseline readout daughter board Readout mother board OSU high voltage distribution board Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 Test “Tube” Results Test module installed into BaBar in August Glue 2 full size prototypes together ⇒ module read out φ using wires & strips read out z using cathode strips integrated into data taking system installed in inner most layer Very good performance/reliability 94% efficiency (acceptance) @ 5600V Extremely valuable experience test several configurations of readout electronics location of bypass capacitor ⇒ near tube is best larger signals, no φ strips, lower multiplicity test grounding scheme study noise and backgrounds efficiency studies (raise/lower HV, disc. thresholds..) The test tube is still working properly inside IR2. Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 BaBar IFR upgrade - LST readout status report Roma 2-3 febbraio 2004 Lettura in PHI – struttura per il trasporto dei segnali dei fili materiale necessario per l’installazione 2004 •FFC Flexible Flat Cable (SLAC) in produzione • •Multistrato (SLAC) in produzione •PHI transition Boards (INFN FE) in produzione (ORDINATO ANCHE IL MATERIALE PER INSTALLAZIONE 2005. PRODUZIONE DIFFERITA A DOPO INSTALLAZIONE 2004) Gianluigi Cibinetto – INFN Ferrara Il Collaudo di un modulo a due tubi equipaggiato di piano di trasporto dei segnali e’ in corso a Princeton, NJ, USA Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 BaBar IFR upgrade - LST readout status report Lettura in Z – struttura multistrato per lettura capacitiva Dettaglio sulle Z transition boards Connettori ( 2 x 8 poli ) per FFC a 16 conduttori FFC a 16 conduttori (6 cavi per piano) materiale necessario per l’installazione 2004 •FFC (SLAC) in ordine A. Cotta Ramusino INFN-FE Nov 2003 Connettori per cavi di segnale microribbon twisted pair Connettori per collegamento schermo cavi di segnale Supporto (PCB) di sostegno e di distribuzione della massa attraverso connettori FASTON Gianluigi Cibinetto – INFN Ferrara •Multistrato (SLAC) materiale ordinato. Produzione differita al termine della produzione dei piani di trasporto segnali •Z transition Boards (INFN FE) in produzione (ORDINATO ANCHE IL MATERIALE PER INSTALLAZIONE 2005. PRODUZIONE DIFFERITA A DOPO INSTALLAZIONE 2004) Commissione Scientifica Nazionale 1 BaBar IFR upgrade - LST readout status report Elettronica di lettura – scheda di Front End: LST-FE Input Analog Daughter (IAD) card INFN -TO 12 prototipi prodotti Collaudo positivo -> ordinata quantita ‘ totale. Lotto per installazione 2004 atteso per fine marzo. LST-FE card INFN -FE 3 prototipi prodotti Collaudo positivo -> ordinata quantita ‘ totale. Lotto per installazione 2004 atteso per fine marzo. Gianluigi Cibinetto – INFN Ferrara Roma 2-3 febbraio 2004 Commissione Scientifica Nazionale 1 BaBar IFR upgrade - LST readout status report Roma 2-3 febbraio 2004 Elettronica di lettura – scheda di Front End: LST-FE Prototipo LST-FE + IAD testato a Princeton su prototipo di modulo completo di piano di trasmissione segnale dei fili: la scheda LST-FE e’ usata in modo stand-alone per misurare il rate dei canali (4 fili + 4 strips) connessi. Il risultato e’ inviato via RS232 al PC di supporto Gianluigi Cibinetto – INFN Ferrara BaBar IFR upgrade - LST readout status report Commissione Scientifica Nazionale 1 LST Crate (con elettronica di monitor), Crate Service Card, FSD Layout of the BaBar LST crate CAN_VCC +5V_CTRL CAN_DOM CAN_ACT CAN_BUS LCD STATUS MODE +5V - 5V RM_ON REMOTE ON/OFF LST CRATE INFN -GE Tutto il materiale per i 13 crate necessari e’ stato ordinato. Lo sviluppo del backplane e delle schede CSC e FSD e’ alla fase di masterizzazione dei prototipi 1 Prototipo completo di FSD atteso per fine marzo. Gianluigi Cibinetto – INFN Ferrara Roma 2-3 febbraio 2004 Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 LST software • Geometria – Accesso alla geometria RPC/LST direttamente dal database di BaBar – Simulazione GEANT4 del rivelatore con LST • Ricostruzione – Studio preliminare del software per la selezione dei µ effettuato tramite Monte Carlo • Integrazione RPC/LST – Ricostruzione degli eventi con compresenza di RPC e LST in sestanti diversi Gianluigi Cibinetto – INFN Ferrara Commissione Scientifica Nazionale 1 Roma 2-3 febbraio 2004 LST Summary • Success of first module validates construction and testing procedures. • Now in full Production at PHT. • Assembly sites at Princeton and OSU in operation • Installation, Electronics, HV, etc. under control and on schedule for summer installation of 2 sextants. • Major challenge: maintaining quality and schedule – – – – 15 tubes per day Q/C is able to keep up Shipments scheduled High quality and high yield Gianluigi Cibinetto – INFN Ferrara